SCPX project, Azerbaijan

SCPX project, Azerbaijan

Execution of five river crossings for the installation of a 48" pipe using the HDD method. Lengths: 645 m, 703 m, 867 m, 964 m, 616 m

Natural gas storage facility Jemgum, Germany

Natural gas storage facility Jemgum, Germany

Crossing of landscape protected area with two 350 t HDD rigs
Lengths: 1,716 m, 1,663 m, 1,528 m
Diameter: well 48“, pipe DN 900
Project report Jemgum

Macedon Field Development Project, Australia

Macedon Field Development Project, Australia

Dune crossing
Lengths: 2 x 890 m
Diameter: 20“, 30“
Project report Macedon Field Development

Pipeline Link Mittelplate, Germany

Pipeline Link Mittelplate, Germany

Connection between offshore drilling platform Mittelplate and onshore facility with five HDD rigs
Lengths: 15,000 m; 6 sections; Diameter: 10“, 6“
Project report Mittelplate

Devil Creek Development Project, Australia (West)

Devil Creek Development Project, Australia (West)

Shore crossing for installation of 16’’ gas pipeline
Length: 2,100 m
Pipe construction and commissioning
Project report Devil Creek Development

Oleoduto RNEST, Brasil

Oleoduto RNEST, Brasil

Three crossings by microtunneling method
Lengths: 170 m, 114 m, 86 m; 56“ steel casing for 46“ oil pipeline
First microtunneling project for Petrobras
Project report Oleoduto RNEST

Qeshm Island

Qeshm Island

Crossing of "Strait of Hormuz“ between Iranian mainland and island Qeshm for installation of 16“ product pipe as connection line
Length: 3,060 m
Project report Qeshm Island